Neenah Construction Update October 12, 2018

Progress this Week:

  • Smith Contracting continued placing flexible base for the roadway widening between Olive Hill and the east end of the project.

Two Week Schedule:

  • Smith Contracting:
    • Continue pond improvement work.
    • Continue Phase IV street and shared use path (SUP) construction.
    • Continue handrail installation at various locations.

Lane Closures:
None scheduled.

General Notes:

  • Residents in Davis Springs have been notified of upcoming work.
  • All work mentioned above is contingent upon weather conditions.

Weather:

  • There were minor weather issues this week. Smith Const. had four working days due to rain showers earlier in the week.