Progress this Week:

  • Smith Contracting:

  • Completed earthwork for the culvert extension.

  • Continued excavation for the proposed shared use path (SUP), between Altona Way and Solera Drive.

  • Excavated to verify existing City of Austin (COA) utilities.

  • Continued pond improvement work.

  • Formed/poured the concrete floor of culvert extension.

Two Week Schedule:

  • Smith Contracting:

  • Begin utility adjustments.

  • Begin forming concrete walls and deck for culvert extension.

  • Continue embankment for the culvert extension and SUP.

  • Continue pond improvement work.

Lane Closures:

  • None scheduled at this time.

General Notes:

  • Residents in Davis Springs have been notified of upcoming work.

  • All work mentioned above is contingent upon weather conditions.